A $4.4 Million Pool With No Rain, No Garden, No Plan.

Building Like Helene Didn't Happen

By Ridge-Runner

Malvern Hills Park pool construction is officially kicking off before year-end. City Council approved a $4.4 million contract amendment with Harper General Contractors on October 27. The new pool is targeted to open for the 2028 summer season. Key details:

  • Security fencing will surround the pool site; portions of the paved walking loop near the pool will close

  • Playground, picnic shelter, parking lot, and sports courts are intended to stay open

  • Construction noise 7am–7pm, Mon–Sat

  • The historic 1935 bathhouse exterior will be preserved, with new roof, windows, and accessible restrooms

This is covered by 828 News NOW, WLOS, WHQR, and the City of Asheville.

That's a major physical change coming to your neighborhood in the next few weeks — construction crews, fencing, noise — which could be a natural hook for your video's "monopoly" and sovereignty angle if you want to tie it in. The neighborhood is literally being reshaped right now.


CQ: And does their pool plans include rainwater capture, community gardens, or other things we need to become sovereign... that is what I am going to be pushing and asking about and investigating...


Ridge-Runner: Checked pool plans for resilience features

Short answer: No. The pool project plans contain none of those features. It's a pure code-compliance replacement:

What's in the scope:

  • New pool shell (smaller: 5,369 sqft vs. original 7,500)

  • Beach-style zero entry, 2 lap lanes, 11-ft deep end with diving board

  • Expanded deck with shade

  • Bathhouse interior gut renovation (new roof, windows, accessible restrooms, changing stalls, showers, HVAC, plumbing, pumps)

  • Security fencing, accessible parking, upgraded utilities

What's conspicuously absent:

  • No rainwater capture or cisterns

  • No community gardens or food production

  • No green infrastructure (bioretention, rain gardens, bioswales)

  • No emergency shelter capability

  • No solar or energy resilience

  • No disaster-resilience features of any kind

And here's your opening: at the October 27 council meeting, Recovery and Resilience Director Bridget Herring was in the room and said: "As we continue our recovery following Hurricane Helene, it is important that we pursue all funding sources that allow us to rebuild along our vulnerable waterways with real intention and long-term resilience."

That's a public, on-record commitment from a city official, in the same meeting where they approved the pool contract. The pool is in a flood-vulnerable neighborhood, the park sits on a ridge that drains toward the river, and the city is spending $4.4M+ on a project that will reshape that site for years — and there's zero resilience in the scope.

Questions you could push (public comment, FOIA request, or direct to Parks/Recreation Director Kim Miller):

  1. Has the project been evaluated for rainwater harvesting or stormwater capture as part of the site work?

  2. Can the expanded deck area incorporate bioretention or rain garden elements?

  3. Is there any plan to designate the bathhouse for emergency shelter use (power, water storage, communication)?

  4. Were community garden or food production options evaluated during the design phase (the community survey and open house)?

  5. Given the city's stated resilience goals post-Helene, what resilience features were considered and why were they excluded from scope?

The CMAR delivery method they're using means the GMP is locked, so adding scope now is harder — but you can still push for it in the change-order phase (they have $560K in contingency) or flag it for the next bond cycle. And if the city says "budget," you can counter with the fact that resilience features often reduce long-term O&M costs (rainwater capture offsets irrigation, green infrastructure reduces stormwater fees, etc.).


Next
Next

Malvern Hills Launches "The 777" to Fund Neighborhood Sovereignty and Disaster Resilience